New order: Vasilikos Power Station, phase IV, unit 5

16-12-2009 - New order: Vasilikos Power Station, phase IV, unit 5

Recently NEM BV secured a new order for Vasilikos Power Station, phase IV, unit 5. Modular HRSG Systems has by now already started the engineering for this project. The new order is a continuation of the successful partnership between IUB and J&P AVAX. Earlier, IUB supplied two HRSGs for unit 4 (photo attached), which have recently been commissioned.

The principal, J&P AVAX, is a Greek EPC contractor. The end customer is Electrical Authority of Cyprus, the most important electricity supplier of the south part of Cyprus. NEM will supply two two pressure level HRSGs, each behind a GE frame 6FA. The gas turbines run on diesel, but in the future it is expected that gas will be available. Two steam turbines convert the steam produced into electricity. The HRSGs will work with highly variable loads, in a so-called 'start-stop' operation. The order includes two bypass systems to be supplied by NEM Power-Systems.